Technical Projects - Capstone
Main contact

Timeline
-
February 1, 2021Experience start
-
February 3, 2021Project Scope Meeting & WalkThrough (Preliminary Data Collection)
-
February 27, 2021Requirements Gathering Specification Document
-
March 27, 2021Traffic Analysis Logical Design
-
April 17, 2021Experience end
Timeline
-
February 1, 2021Experience start
-
February 3, 2021Project Scope Meeting & WalkThrough (Preliminary Data Collection)
Meeting between students and company to confirm: project scope, communication styles, and important dates.
-
February 27, 2021Requirements Gathering Specification Document
Students report of initial data findings, computer use surveys, individual interviews, and any other data collection activities used, to outline the areas of concern in the sponsor network.
-
March 27, 2021Traffic Analysis Logical Design
Students report of the findings of the Traffic Analysis and present detailed solutions, where necessary, to address areas of concern or need withing the network.
-
April 17, 2021Experience end
Experience scope
Categories
Information technologySkills
competitive analysis business consulting communication researchThe process of analyzing and designing a new network or designing a network upgrade is a formal process. There are distinct phases involved in the design process of a network, of which any or all can be applied to any network. Students working on this project will concentrate on the first four phases of the network design process; Requirements Gathering, Traffic Analysis, Logical Design, and Physical Design. Installation and Maintenance, will not be a focus of the course.
Company partners will benefit from having a student group conduct a detailed analysis of their existing network infrastructure, as well as an analysis of the present and future needs of the user population. Any areas where the user needs are not presently met, will have practical solutions designed to address these areas of concern.
Practical exercises will be used wherever possible to reinforce student learning and help directly involve the company partner to better ensure appropriate solutions are developed..
Students
Requirements Gathering Specification Document
- an outline of computer user needs and areas of concern affecting employee effectiveness and productivity
Traffic Analysis Specification Document
- an outline of the functional characteristics of the existing network infrastructure
Logical Design Specification Document
- itemized hardware/software solutions designed to optimize the network environment
Physical Design Specification Document
- detailed costs and implementation schedule
Project timeline
-
February 1, 2021Experience start
-
February 3, 2021Project Scope Meeting & WalkThrough (Preliminary Data Collection)
-
February 27, 2021Requirements Gathering Specification Document
-
March 27, 2021Traffic Analysis Logical Design
-
April 17, 2021Experience end
Timeline
-
February 1, 2021Experience start
-
February 3, 2021Project Scope Meeting & WalkThrough (Preliminary Data Collection)
Meeting between students and company to confirm: project scope, communication styles, and important dates.
-
February 27, 2021Requirements Gathering Specification Document
Students report of initial data findings, computer use surveys, individual interviews, and any other data collection activities used, to outline the areas of concern in the sponsor network.
-
March 27, 2021Traffic Analysis Logical Design
Students report of the findings of the Traffic Analysis and present detailed solutions, where necessary, to address areas of concern or need withing the network.
-
April 17, 2021Experience end
Project examples
- Security Analysis
- Cable Management
- Workstation and Server Performance
- Backbone Traffic - Capture and Analysis
- Workstation Ergonomics
Additional Community Partner criteria
Community Partners must answer the following questions to submit a match request to this experience:
-
Q1 - Checkbox
-
Q2 - Checkbox
-
Q3 - Checkbox
-
Q4 - Checkbox
Main contact

Timeline
-
February 1, 2021Experience start
-
February 3, 2021Project Scope Meeting & WalkThrough (Preliminary Data Collection)
-
February 27, 2021Requirements Gathering Specification Document
-
March 27, 2021Traffic Analysis Logical Design
-
April 17, 2021Experience end
Timeline
-
February 1, 2021Experience start
-
February 3, 2021Project Scope Meeting & WalkThrough (Preliminary Data Collection)
Meeting between students and company to confirm: project scope, communication styles, and important dates.
-
February 27, 2021Requirements Gathering Specification Document
Students report of initial data findings, computer use surveys, individual interviews, and any other data collection activities used, to outline the areas of concern in the sponsor network.
-
March 27, 2021Traffic Analysis Logical Design
Students report of the findings of the Traffic Analysis and present detailed solutions, where necessary, to address areas of concern or need withing the network.
-
April 17, 2021Experience end